Process Flow Chart of Garments Cutting Section
What is Cutting in Garments?
Cutting is one of the major processes in garments manufacturing. Here garments parts are cutting according to the pattern. In the garments cutting department, a process flow chart has to be maintained to send the right measurement parts in the next process for making quality garments. As its importance in garments manufacturing, a process flow chart for the garments cutting department is presented in this article.
Process Flow Chart of Fabric Cutting Department:
Pattern received from pattern department
↓
Cutting ratio received from the merchandiser
↓
Marker making
↓
Fabric received from the store
↓
Fabric Checking
↓
Fabric Spreading
↓
Marker placing on to the lay
↓
Cutting the fabric
↓
Numbering
↓
Checking
↓
Sorting and Bundling
↓
Send to the sewing department
Each process of garments cutting flow chart is discussed shortly in the below table:
S/L
|
Process
|
Job
|
01
|
Pattern received from pattern department
|
At first, you have to receive different sizes of patterns for each style of garments from the pattern department.
|
02
|
Adipex) 5pt; mso-border-left-alt: solid windowtext .5pt; mso-border-top-alt: solid windowtext .5pt; padding: 0in 5.4pt 0in 5.4pt; width: 2.0in;” valign=”top” width=”192″> Garments cutting ratio received from the merchandiser
|
The cutting ratio for each style garment should be received from the merchandiser
|
03
|
Marker making
|
To complete the cutting process easier, you have to make a marker for each style of garment.
|
04
|
Fabric received from the store
|
In the mean time, you have to receive fabrics from the store for each style of garments.
|
05
|
Fabric Checking
|
Here, fabrics have to be checked and confirm the shade variation of free fabrics in the cutting table.
|
06
|
Fabric Spreading
|
When the above process is completed, then you have to spread the fabric with the correct lay height and ply tension.
|
07
|
Marker placing on to the lay
|
After that, the marker has to be placed on the top layer of the lay.
|
08
|
Cutting the fabric
|
Here, fabrics have to cut by maintaining a marker.
|
09
|
Numbering
|
After cutting the fabrics, each part of different style fabrics should be numbered to avoid mixing with the other style fabric parts.
|
10
|
Checking
|
Checking the cutting fabrics accurately by comparing with its marker.
|
11
|
Sorting and Bundling
|
Cutting parts should be sorting and bundling here to send easily into the next process.
|
12
|
Send to the next process.
|
Cutting fabric parts have to be sent into the next process (where required) like printing, Embroidery, sewing, etc.
|